Since 2006, Kytom has been managing operations on occupied sites according to a logic of calibrated project phases. Each phase covers 150 to 250 m² deliverable in 2 to 3 weeks, with a secured buffer zone and a schedule communicated to teams 15 days before the start. Our 11 agencies deploy a site manager dedicated to phasing, who coordinates internal relocations, furniture deliveries and technical interventions. Across 1,200+ delivered projects, 94% have respected the planned cohabitation without interrupting business activity. We systematically include an internal communication contact on the client side, validate noisy slots outside meeting hours, and measure acoustics at the zone boundary to stay below the 55 dB(A) recommended by ANACT.